Ministry Center Update #7

Entry Way 2Partial Sheeting of North WallNorthWall Sheeting and Insulation Completed

The steel erectors have been busy.  The picture on the far left shows the forms for the concrete columns that are located at the main entrance to the building. The center picture taken from the lake side of the building shows the north wall partially sheeted.  The picture on the right is taken from the parking lot side and shows the north wall completely sheeted and insulated.  The erectors have stopped sheeting for the moment while the work out a problem with the insulation manufacturer.  They continue to work in other areas of the building. 

The site contractors finished laying the domestic sewer lines Wednesday and installed manholes on Thursday.  They will begin work on the storm sewer lines this coming Monday.   Stay tuned for more updates.  PW

April 25, 2008 Posted by wbauer | Ministy Center Updates | | No Comments

Ministry Center Update #6

Steel ArrivingDay 2 Erecting Steel

Much has happened over the past week.  The “Ministry Center” is beginning to take shape.  The steel arrived at 7:00am Tuesday, right on schedule.  It is amazing to me that a 7,000 square foot building can fit on two flat-bed semi trailers.

As soon as the steel was unloaded they began erecting it and by Wednesday evening both sides, one end and three of the roof trusses were securely in place.  The steel should be completely erected by the end of today and I expect the roof and walls to follow shortly.  I’ll keep you updated. PW

April 17, 2008 Posted by wbauer | Ministy Center Updates | | 2 Comments

Ministry Center Update #5

Writing Scripture on FoundationFoundation Scripture

Last Sunday several people went out to the property after church to view the progress on the Ministry Center and to write scriptures on the foundation.  It was beautiful to see young kids, teens and adults writing scripture verses on the foundation.

We also annointed the entrance and prayed that God would help all who enter to find hope, healing and compassion and all who leave to do so in peace.

Not much is happening on the buidling.  At the moment we are waiting for the steel to arrive.  It is supposed arrive at 7:00am on Aprll 15.  When it arrives they will immediately begin erecting it and should have the building up and enclosed within 3 weeks. YES!!!  That’s it for now. PW

April 10, 2008 Posted by wbauer | Ministy Center Updates | | No Comments